Huizhou Boluo 100MW Ground-Mounted Centralized Solar Power Station

This ground-mounted centralized solar reference project in Boluo, Huizhou, Guangdong, China demonstrates how a carefully engineered 100MW installation converts an unavoidable operating cost into a predictable, long-term saving.

Project Snapshot

System TypeGround-mounted Centralized Solar
LocationBoluo, Huizhou, Guangdong, China
Installed Capacity100MW
Annual Generation120,000,000 kWh
Annual Electricity Savings199,800,000,000 VND
Payback Period10 years
Annual CO2 Reduction80,000 tonnes

Project Background and Objectives

Utility-scale ground-mounted generation demands a different discipline from rooftop work: land utilisation, grid-code compliance, string architecture, and long-term operations and maintenance planning all have to be resolved before a single pile is driven. This project was developed to deliver bulk clean energy at a levelised cost well below the local commercial tariff.

Engineering Approach

Development followed a utility-grade sequence: geotechnical investigation, irradiance and soiling modelling, single-line diagram design and grid-code compliance review, followed by pile layout optimisation and string sizing that keeps DC/AC ratio within the inverter's efficient operating window. Modules are mounted on hot-dip galvanised steel structures rated for the local wind zone, with row spacing set to avoid inter-row shading at the winter solstice. The plant is monitored at string level, and meteorological stations provide irradiance and module temperature data for performance-ratio reporting.

Verified Results

  • Annual clean generation of 120,000,000 kWh from the installed array.
  • Grid electricity expenditure reduced by 199,800,000,000 VND every year.
  • Carbon emissions cut by approximately 80,000 tonnes CO2 per year.
  • Investment recovered within 10 years, with an expected service life of 25 years or more.
  • Performance monitored remotely with string-level fault alerts and monthly yield reporting.

Why This Project Matters

Projects at this scale move the needle on national renewable targets, but their real value is measured in levelised cost and reliability. This plant shows that centralised solar in Vietnam can be engineered to utility standards, delivered on schedule and operated with transparent performance reporting - the three conditions institutional investors require before they commit capital to the sector.

About Hengyang New Energy
Hengyang New Energy Vietnam Company designs, engineers and delivers photovoltaic and energy storage systems for households, enterprises and public institutions across Vietnam and the wider region. From a 3 kW rooftop system to a 200 MW ground-mounted station, every project is supported by in-house structural and electrical engineering, grid-connection compliance management and lifetime performance monitoring.

If you would like a feasibility assessment, a yield forecast or a firm quotation for a site of your own, our engineering team can prepare a proposal within five working days.